Tata Autocomp Green Gotion Energy Solution Pvt. Ltd.
Total Sq. feet :- 2,50,000 Sq. feet.
Drawing proposal & Approval :- 2 weeks.
Material Supplied :- 30 Days
Installation work :- 60 Days
Total Man Power :- 58
Safety officer :- 2, Supervisor :-2, Office boy :-1
Skilled Worker :- 7, Semi skilled worker :-30
Un Skilled worker :- 18
Total Project Completion Day :- 90 Days