General Electric, Chakan.
Total Sq. feet :- 1,50,000 Sq. feet.
Drawing proposal & Approval :- 2 weeks.
Material Supplied :- 30 Days
Installation work :- 60 Days
Total Man Power :- 45
Safety officer :- 2, Supervisor :-2, Office boy :-1
Skilled Worker :- 5, Semi skilled worker :-25
Un Skilled worker :- 10
Total Project Completion Day :- 90 Days