Mahindra & Mahindra, Durr. Chakan M.H.
Total Sq. feet :- 1, 50,000 Sq. feet.
Drawing proposal & Approval :- 2 weeks.
Material Supplied :- 45 Days (30 hold due to Covid)
Installation work :- 60 Days
Total Man Power :- 35
Safety officer :- 1, Supervisor :-2, Office boy :-1
Skilled Worker :- 5, Semi skilled worker :-16
Un Skilled worker :- 10
Total Project Completion Day :- 105 Days