Ferrero India Pvt. Ltd.
Home Ferrero India Pvt. Ltd.

Ferrero India Pvt. Ltd. Baramati.

Total Sq. feet :- 80,000 Sq. feet.

Drawing proposal & Approval :- 2 weeks.

Material Supplied :- 45 Days

Installation work :- 60 Days

Total Man Power :- 30

Safety officer :- 1, Supervisor :-2, Office boy :-1

Skilled Worker :- 5, Semi skilled worker :-15

Un Skilled worker :- 6

Total Project Completion Day :- 105 Days